|
The Glasgow
Municipal Tramways System
(Extracts from)
The Tramway and Railway World
September 7th 1911
It is now fully eight years
since the annual conference of the Municipal Tramway Association
was last held in Glasgow. It is a long cry from July, 1903, to
September, 1911, and members of the Association who have not kept
in close touch with northern developments will find when they visit
Glasgow in the closing days of the present month for the forthcoming
conference that many tramway developments have taken place in the
interval as regards extension of lines, additions to power plant,
additions to depots and rolling stock, and general expansion of
the undertaking. They will also find that on the financial side
the tramways show a splendid record. To aid members in their examination
of one of the most successful and largest tramway undertakings
of the country we here present a description which embodies some
of the main points which have appeared in previous articles, eliminates
those which have been superseded, and brings the information right
down to the present time.
As is generally known, the
tramway lines in Glasgow were never owned by a company. The original
tracks were laid down by the Corporation in 1871 and succeeding
years, and the system was leased for 23 years to the Glasgow Tramway
and Omnibus Company, who worked it by horse traction down to 1894.
When the close of the lease approached the Council and the company
failed to come to terms for its renewal. The result was that, under
Parliamentary powers granted to the Corporation as far back as
1870, the latter determined to work the lines themselves. The late
Mr. Walter Paton was appointed convener of the Tramways Committee,
and Mr. John Young became; general manager. Under their guidance
the new municipal horse car service was started on July 1,
1894, and it was also during their rule that electric traction
was afterwards inaugurated and the new system developed in a wonderfully
prosperous way. Before Mr. Paton died he saw the undertaking an
assured permanent success, and it was after that stage had. been
reached that Mr. Young resigned in order to devote his talents
to other schemes requiring powers of organisation, and Mr. James
Dalrymple succeeded to the general managership. When the Corporation
began working the lines they extended to only 31 miles of
route, double track, but they rapidly increased in length, until
at the present time the routes aggregate 98 1/2 miles. From the
very first a profit was made after allowing for interest and sinking
fund.
After prolonged investigation,
involving among other things visits by deputations to the Continent
and to the United States, the Town Council decided early in 1897
to try the overhead trolley wire system of electric traction, and
the first line, which was regarded as experimental, was opened
for traffic on October 13, 1898. It extended from the centre of
the city to Spring-burn in the northern outskirts, a small temporary
power-station being erected near the outer terminus. In November
of the following year an extension to the south side of the Clyde
came into use, giving a total of five miles of route electrically
worked.
The results obtained were
so satisfactory that the Corporation on January 5, 1899, resolved
that the whole tramway system of Glasgow should be changed to the
electric trolley wire system. Mr. H. F. Parshall, M.InstC.E. (now
chairman of the Central London Railway Company), was appointed
consulting engineer, and on his recommendations it was decided
that the tramway power plant should be altogether distinct from
that for electric lighting, that one central generating station
should be provided for the entire undertaking, and that the three-phase
high-tension system of transmission to substations distributed
throughout the city should be adopted. The Glasgow tramways were
thus the first in the country to adopt three-phase transmission
on a large scale. A site for the power-station was chosen at Pinkston,
near Port Dundas, on the north side of the city, bounded on three
sides by the Forth and Clyde Canal and the Caledonian and North
British Railways. The work was pushed on vigorously, sub-stations
were provided wherever required, a number of the lines began operating
electrically in April, 1901, and very soon afterwards the last
horse car disappeared. Since then the record has been one of steady
expansion in length of lines, power and distributing machinery,
business done, and financial results.
PRESENT EXTENT
OF THE UNDERTAKING.
At the present time all
extensions have been completed, the last Parliamentary Act having
been granted in 1909, and the mileage stands at 98 miles, double
track. With the exception of a short length measuring one mile
within the burgh of Paisley, over which Glasgow Corporation
have running powers, the entire track is maintained by the Glasgow
tramway department. The lines in Govan, extending to 4 miles 2
1/2 furlongs, while owned by the Corporation of Govan, are leased
to Glasgow ; and by agreement the Glasgow Corporation took
over the Clydebank Tramways Order of 1901, to construct and
work the tramways (5 miles) within the burgh of Clydebank as part
of the Glasgow system'. A short length of this (2 1/2 furlongs)
is, meantime, being worked by the Dumbarton Burgh and County Tramways,
Limited. In all there are 59 miles of double track within the city
boundary and 39 miles without. The maps here reproduced show the
system, its connections with other systems, and the positions of
the power-station, sub-stations, and depots. The steepest gradient
is 1 in 12, and the radius of the sharpest curve is 31 ft.
PERMANENT
WAY.
When the system was converted
from horse to electric traction the entire track was renewed throughout.
The method of construction then adopted was, briefly, as follows:
A 6 in. bed of concrete was laid over the entire width of track
extending to 18 in. beyond the outside of the rails ; the rails,
60 ft. long, 7 in. deep, with 7 in. bottom flange, and weighing
98 lb. per yard, were laid and fished with plates 31 in. long,
having eight 1 in. bolts, the holes being staggered. The rails
were laid and packed with fine concrete well rammed and Hushed
to the underside of the rail. The paving, chiefly of hard granite
setts, square dressed, was laid on a bed of sand, and grouted with
a mixture of coal-tar pitch, and creosote oil. Four and a half
miles of track laid as above, but having joints electrically welded
by the Lorain Steel Company's process, are still giving satisfaction.
There are also over 20 miles of track welded by the Thermit process,
and at present the department are relaying Renfield Street, the
part of the track where the traffic is greatest, and are having
the joints electrically welded by the Tudor Accumulator Company's
process. In this portion of the track anchors consisting of pieces
of old rails have been embedded in the concrete every 10 ft., and
the rails are held in position by bolts. The question of smooth
paving has been very much in evidence of late. The results from
ashphalt paving alongside tram rails in Glasgow have been rather
disappointing, and in order to prevent the rutting caused by vehicular
traffic, the department have introduced a smooth-dressed granite
stone, 12 in. wide, along the outer side of the outside rail with
good results.Wood paving has been used to some extent, but there
have been laid down in the centre of the city several stretches
of track paved with granite stones 6 in. wide, 9 in. long, and
6 in. deep, tooled or nidged on the surface, having perfectly square
sides fitting close at the joints, and laid on a bed of cement
mortar. The results, so far, have been very satisfactory, giving
an almost noiseless surface.
Glasgow
Tramways, Showing Position of Power-Station, Sub-Stations and
Depots
A great many of the recent
extensions and renewals have been laid on cross sleepers. The sleepers
are best quality pitch pine, 7 ft. long, 11 in. broad on the sole,
10 in. broad on the top, and 4 1/2 in. thick, laid at 3 ft. centres
on a bed of concrete 4 in. thick. The rails are fixed to the sleepers
either by coach screws or dog spikes, and after being lined and
levelled are boxed in with concrete up to the underside of the
rail. Since 1905 the British standard rail has been adopted, using
section 5 on straight track, and 5c on curves, with the standard
six-holed fish plate. Various lengths of track have been laid with
continuous rail joint fish plates. These have not yet been in use
a sufficiently long time to express any opinion as to their merits.
All fish-plated joints are bonded with two 28 in. bonds, .0000
B.and S., with cross bonds every 40 yards. Drawings of the joints
are given herewith. All renewal work up to the present has been
carried out during the night, as this work has chiefly been in
the centre of the city where it would be impossible to use temporary
lines or crossovers. This also applies to the renewals of junctions.
These, as far as possible, are laid piecemeal, but where rendered
necessary by alterations, even the most complicated have been renewed
in one shift of five hours. The majority of the crossings in special
work-are of the iron bound type, having renewable centre pieces.
There are also crossings composed entirely of manganese steel.
The points are of a standard length, 12 and 14 ft., constructed
in cast steel with forged tongues, also in solid manganese steel.
In order to have the maintenance of the track efficiently carried
out, the system has been divided into sections, these varying in
length with the amount of car traffic. Over each section there
is one foreman with a squad of from 14 to 20 men. There are also
two chief foremen, each controlling one-half of the track, with
10 foremen under him.

The depot for permanent
way material is in close proximity to the Coplawhill car works.
It is a yard of considerable size, where all rails, points, and
crossings are stored, and where all curves, special work, etc.,
are built up, and to which all disused rails, points, crossings,
etc., are returned. At present new offices, stores, and workshops
having machine tools, rail bender, etc., are being erected. In
addition, there are three subsidiary yards throughout the city,
all connected up by sidings. These are used for storing setts,
pitch, sand, etc. ; these materials are conveyed by trucks constructed
on the double-bogie principle. These also run alongside the
wharf, where setts, metal, etc., are discharged, and taken to the
various points where required.
The following is the chemical
composition of the rails as specified :
Carbon.. .. .. .....4 to
55 per cent.
Manganese .. .. .8 to 1
per cent.
Phosphorus .. .. Not to
exceed .8 per cent.
Sulphur .. ......... Ditto.
Silicon ,, ,, ,. .....1
per cent,
PINKSTON GENERATING
STATION.
The main generating station
is situated in the northern district of the city, on the north
bank of the Forth and Clyde Canal, at Pinkston. The ground, which
was purchased on May 4, 1899, extends to 18,997 sq yards. The building
consists of a steel framework cased in brick and plaster. The building
is 244 ft. long by 200 ft. broad, and 88 ft. high inside. The station
is divided into three sections, viz., boiler room, 244 ft. by 84
ft.; engine room, 244 ft. by 75 ft. ; auxiliary plant room, 244
ft. by 40 ft. The height of the boiler room is 70 ft., that of
the engine room 64 ft., and that of the auxiliary room 52 ft. The
two chimney stacks are built of brick, with ornamental stone and
terracotta mouldings. The total height of the stacks is 263 ft.,
the internal diameter is 16 ft., and the width across the base
is 50 ft. Boiler Room. The boiler room is equipped with
twenty-two Babcock and Wilcox water-tube boilers, with the Scotch
type furnace, with internal superheaters and the makers' mechanical
chain grate stokers. The boilers are arranged in eleven batteries
of two boilers each, five batteries on one side and six on the
other. The original equipment consisted of sixteen boilers capable
of producing 20,000 lb. of steam per hour at a working pressure
of 160 lb. per sq. in., with a superheat of 75 deg. Fahr. The boiler
tubes are 18 ft. long and 4 in. in diameter, with a heating surface
of 5,173 ft., the grate area being 63 sq. ft. The six larger boilers
installed in 1909 have a capacity of 25,000 lb. of steam per hour
at 160 lb. pressure, with a superheat of 130 deg. Fahr. These boilers
are fitted with tubes 18 ft. long aid 4 in. in diameter, with a
heating surface of 6,182 sq. ft., the grate area being 100 sq.
ft. Each side of the boiler house, with its batteries of boilers,
is equipped with an independent coal and ash conveyor, coal storage,
economiser, flue, and shaft.
The motors driving the stokers
are placed in the basement of the boiler room. There is one direct-current
motor at each end and one alternating-current motor in the centre
of each of the common driving shafts, the two driving shafts running
the whole length of the boiler batteries, one on each side under
the floor, so that each shaft can, in case of emergency, be driven
from any of the motors. The water for the boilers is supplied from
the Corporation mains to two storage tanks placed on girders between
the two chimneys, and they hold 36,000 gallons. Each of the two
fuel economisers is capable of dealing with 18,000 gallons of water
per hour and raising its temperature from 90 deg. to 160 deg. Fahr.
The furnace gases discharge
into two overhead flues, constructed of Siemens-Martin steel plates.
The length of each flue is 242 ft. and the width 8 ft. The flues
are covered throughout their entire length with asbestos and magnesium
lagging respectively.
Coal and Ash Handling. Coal
is brought to the generating station by two railways the North
British and the Caledonian the lines terminating in specially constructed
sidings. The outside coal bunkers have a capacity of about 4,000
tons. There are six tracks and eight hoppers for the Caledonian
Railway (high level), and one track and two hoppers for the North
British Railway (low level). The railway wagons are tipped directly
into the bunkers by two electric locomotives fitted with swivelling
cranes, and all shunting operations are carried out with the same
locomotives.

The coal is carried from
these outside bunkers to storage bunkers built over the top of
the boilers by two mechanical bucket conveyors, built by the Mirrlees
Watson Company. The bunkers over the boilers have a capacity of
about 2,400 tons. Each conveyor can handle 50 tons per hour, and
runs at a speed of 45 ft. per minute. The coal passes from the
overhead bunkers into the boiler hoppers through specially designed
shoots with weighing arrangements. The ashes are handled by the
coal conveyor, the buckets being filled by four fillers from shoots
under the boiler ash-bins. The conveyors take the ashes up to the
top of the boiler room, and discharge them into a specially constructed
ash-bin built at the end of the boiler room, from which they are
shot into carts for removal. The boiler feed-piping is arranged
on a double ring system, either the steam or electric pumps being
able to supply the boilers. The water is taken from the hot wells,
and passes through meters to the economisers and into the boilers,
the water passing from the condensers through a Harris-Anderson
water purifier back into the hot wells, which are replenished from
the storage tanks. The steam piping is extremely short and simple,
one main header running the whole length of the boiler house ;
from which the necessary branches are taken.
Engine Room. Two
overhead electric three-motor travelling cranes, of 75 ft. span,
are installed in the engine room, each being rated to lift
50 tons. The original steam plant consists of four three-cylinder
vertical compound engines rated at 4,000 h.p. each ; two two-cylinder
vertical cross-compound engines rated at 800 h.p. each, and six
two-cylinder compound high-speed engines of the enclosed type rated
at 100 h.p. each. Two of the four main engines were made by the
Allis Company of Milwaukee, and the other two by Messrs. Musgrave
and Sons, Bolton. Messrs. D. Stewart and Company, Glasgow, supplied
the two 8oo-h.p. engines, and Messrs. W. H. Allen, Son, and Company,
Limited, Bedford, the six small engines.
The Allis engines are of
the Reynolds-Corliss type, and run at 75 revolutions per minute,
with 150 lb. steam pressure. The cylinders measure 42 in., 62 in.,
and 62 in. in diameter, with a 60 in. stroke. The cylinders are
furnished with the Reynolds-Corliss automatic double-ported valve
gear, each with two eccentrics. The governor is of the weighted
type, operating both high and low-pressure cylinder valve gears.
The high-pressure cylinder is steam jacketed, and a reheater receiver
is fitted between the high and low-pressure cylinders. The flywheel
is 24 ft. in diameter, and weighs about 220,000 lb. The total weight
of the engine complete is about 700 tons, and, with the generator,
about 790 tons.

Engin Room Vertical Engins, Generators
and Turbo-Generator
The results of the official
tests on No. 1 engine showed a steam consumption of 12.2 lb. of
steam per 1. h.p. hour, and on No. 2 engine a consumption
of 12.4 lb. per i.h.p. hour. The Musgrave engines are of a somewhat
similar design to those previously described. The sizes of the
cylinders are: High pressure 42 in., low pressure each 60 in. in
diameter, with a 60-in. stroke. The shaft is in two pieces, together
weighing about 82 tons. The valves are of the Corliss cylindrical
type, with Musgrave trip motion, worked by eccentrics from the
main shaft. The governing gear is similar to that on the Allis
engines. A reheater is fitted between high and low-pressure cylinders.
The steam consumption during the official trials in June, 1902,
showed that the steam per i.h.p. hour was 13.4 lb. for No. 3 engine,
and 13.2 lb. for No. 4 engine.
Owing to the increased requirements
for power, it was decided in 1907 to install a steam turbo-alternator.
A 3,000 kw., 1,500 revolutions per minute turbine of the Brown,
Boveri-Parsons type, manufactured by Messrs. Richardsons,Westgarth,
and Company, Limited, of Hartlepool, was finally installed and
put on load in June, 1909. This turbine is specified to give 25
per cent, overload continuously without the use of a bye pass,
and 50 per cent, overload with the bye pass in action; the guaranteed
steam consumption at full load is 14.85 lb. per kilowatt-hour,
with a steam pressure of 150 1b. per square inch, and steam superheated
to 300 deg. C. The turbine is provided with the makers' emergency
cut-out gear, which automatically releases a helical spring on
the stop valve spindle, thereby closing the stop valve whenever
the speed exceeds a certain predetermined value. The preliminary
official steam tests taken on this turbine show that the makers
are well within their guaranteed figures. Owing to the economical
results obtained from the turbine, it has been decided to install
another turbine of 5,000 kw. capacity.
The 800-H.p. Stewart engines
are of the two-cylinder, vertical, cross compound type. The six
auxiliary Allen engines are of the high-speed, compound, two-crank,
enclosed type, rated at 100 h.p. at a speed of 300 revolutions
per minute.
Automatic Oiling System. The " Siegrist " automatic
oiling system is installed on the Allis, Musgrave, and Stewart
engines. The cylinder oil and engine oil are pumped by steam pumps
from tanks in the oil filter room to an overhead divided tank.
From this tank the oil is delivered by steam pumps to the separate
engine units. After lubricating the engines, the oil gravitates
from the crank pits through the filters to the engine oil tank
in the oil filter room.
Generators. The
four three-phase generators for the reciprocating steam engine
sets were supplied by the British Thomson-Houston Company,
Limited, and built in America by the General Electric Company.
Each machine has a nominal capacity of 2,500 kw. at 6,500 volts
when running at a speed of 75 revolutions per minute. The machine
has 40 poles, thus giving a frequency of 25 cycles per second.
The machines have stationary armatures, the armature frame being
arranged on sliding foundation plates, allowing the frame to be
moved clear of the field. The construction of the armature windings
allows of any coil being removed and replaced without disturbing
more than six adjacent coils. There are 120 coils, each coil having
18 turns. The revolving field pole-pieces are built of sheet iron,
securely fastened to the periphery of the flywheel. The field coils
are made of strip copper wound on edge.
The normal excitation of
the field at full non-inductive load is 250 amperes, or, at full
inductive load, at 80 per cent, power factor, 345 amperes.
The excitation current is taken from the 100-volt exciter circuit.
The generators are capable of carrying 25 per cent, overload for
a long period, and are guaranteed to stand 50 per cent, overload
for 15 minutes without injury.
The two-pole three-phase
alternator for the 3,000-KW. turbine set was supplied by Messrs.
Brown, Boveri, and Company. At unity power factor the output is
3,000 kw. at 6,600 volts ; it has an overload capacity of 25 per
cent, for two hours and 40 per cent, for one half-hour, with a
maximum temperature rise on full load of 45 deg. C. The full load
efficiency is 95 per cent. Cool air, delivered under pressure after
passing through a filter, is drawn into the windings of the machine
at both ends, the air entering at the base and being discharged
at the top.
The 500-volt. B.T.H. direct-current
generators (which are coupled direct to the Stewart engines), when
running as shunt machines at 500 volts, are rated at 500 kw., and
at 600 kw. when running as compound machines at 600 volts at a
speed of go revolutions per minute. These sets are used to supply
current to the system during the time the cars are not in service,
and are also used, in conjunction with two rotary converters installed
in the pump room, to relieve the main engines at times when the
load on the power-station is slightly more than a full load for
the main generators running. The six auxiliary generators were
also supplied by the British Thomson-Houston Company, and have
a capacity of 50 kw. each at 100 volts when running at a speed
of 300 revolutions per minute. The machines are shunt wound and
employed to excite the fields of the main generators, and to supply
current for the station lighting.
Auxiliary Room. The
auxiliary room contains the whole of the condensing plant in connection
with the reciprocating sets in the engine room, and also the boiler
feed pumps, rotary converters, and the water purifier. The condensing
plant consists of five surface condensers built by the Mirrlees
Watson Company. There are four condensers capable of dealing with
60,000 lb. of exhaust steam per hour, and one condenser capable
of dealing with 24,000 lb. per hour. Each condenser is provided
with a three-throw Edwards air pump driven by a motor. The circulating
water centrifugal pumps are also electrically driven, and were
supplied by Messrs. Mavor and Coulson. Four of the pumps have a
capacity of 240,000 gallons of water per hour, and one has a capacity
of g6,ooo gallons per hour. Each pump receives the water from the
canal through separate pipes about 25 ft. long, and discharges
into a common pipe leading into the canal.
Five feed pumps are installed
four electric ally-driven ones by the Mirrlees Watson Company,
and one steam pump by Messrs. G. and J. Weir, Limited. The first
have a capacity of 8,000 gallons of water per hour against a steam
pressure of 160 lb. The Weir steam pump has a capacity of 16,000
gallons per hour when running at its normal speed of 12 double
strokes per minute. The feed water purifier supplied by Messrs.
Harris, Anderson, and Company, has a capacity of 22,000 gallons
per hour. The feed water from the condensers is received into a
mixing tank, where alum and soda are added, and passes through
a series of tank filters packed with special wood fibre.

Auxiliary
Room
The two rotary converters
installed in one corner of the auxiliary room are used for two
purposes, viz., converting the three-phase high-tension current
into 500-volt direct current for the power supply of the generating
station when the direct-current generators are not running; and
also, as previously mentioned, to convert the 500-volt direct current
received from the Stewart setts into three-phase current.
The condensing plant for
the 3,000-KW. turbine is capable of dealing with 50,000 lb. of
steam per hour, and is fitted with a "Lea" recorder.
The whole of the plant was supplied by the Mirrlees Watson Company,
and practically is on the same lines as that previously described.
Two additional boiler feed pumps are placed alongside this condenser.
Switchboard . Considerable
trouble was given by the original switch gear at Pinkston, the
air-break switches being chiefly at fault, and in 1904 it was decided
to scrap this gear and install a modern electrically-controlled
system with oil-break switches. Owing to want of space, considerable
difficulty was met with when drawing up the plans for the new installation.
It was finally decided that the Corporation engineers would be
responsible for the designs of the general installation, and on
this arrangement contracts for the generator and rotary transformer
switches were let to the British Thomson-Houston Company, and for
the feeder switches to the Westinghouse Company.
The installation is arranged
on three floors. The ground floor contains the dividing bell-mouths
for the incoming generator and rotary cables, the outgoing feeder
cables to the substations and to the generating station of
the Corporation electricity department; also all instrument transformers,
synchronising transformers, and the cable spark-gaps. The
second floor, on the engine room floor level, contains the main
oil switches, and the third floor carries the two bus-bar chambers
extending the whole width of the engine room, with oil-break switches
at each end for inter-connecting the two sets of bus-bars and forming
a ring bus-bar. In the design of the switch gear, care has been
taken to isolate each phase by a 4 1/2 in. brick wall. To enable
the connections of the switch gear to be readily followed, and
to give at the same time a short description of the type of gear
installed, a start is made from the main generators. Two 0.2 sq.
in. three-core cables run in ducts from each main generator through
the foundation of the machines to the ground-floor compartment
of the gear. These cables end in two simple lead bell-mouths, filled
in with paraffin wax, with a layer of hard bitumen over the top
of the wax. From the lead bell-mouths three single-core rubber
cables are taken through porcelain insulators to their respective
phase compartments. A series transformer is inserted in each phase,
these transformers supplying the current to the ammeters, watt-meters,
etc. The cables then pass to the isolating switches and to the
incoming terminals of the British Thomson-Houston non-automatic
generator oil-switch, and at this point tappings are taken off
each phase to three sets of potential transformers supplying current
to the three independent synchronising circuits, and to the potential
transformers for the power factor indicators. The main oil switch
is of the well-known British Thomson-Houston type operated by a
series motor. The switch has a carrying capacity of 500 amperes.
Instrument and Control Boards in
Pinkston Power Station
The outgoing cables are
led up the back of the oil switch to knife-pattern isolation switches,
thence to the bus-bar chamber on the second floor, the cables passing
through the floor in porcelain insulators to the double set of
selector switches. Solid copper connections are taken from these
selector switches through the brickwork on to the main and
auxiliary bus-bars. The main bars are in sections, one generator
being coupled to each section; these sections may be interconnected
by knife section switches. From each section of the main bus-bars
five three-core high-tension feeders are taken off. The supply
to the feeders is taken off the main busbar by single-core
rubber-covered cables, each one of these cables supplying two feeders
(with the exception of the cables taken off the live end of the
selector switches on Nos. 2 and 3 generators). These single cables
pass through the floor on to the top jaws of knife-pattern isolating
switches, and it is at this point that the connections are taken
through the brickwork to the knife isolating switches immediately
behind the particular isolating switches in question. From the
isolating switches the circuit is continued to the automatic
oil-break feeder switches. These switches were made by the Westinghouse
Company, and both the closing and tripping circuits are controlled
by solenoids. Passing through the switch, the cables are carried
through the switch room floor on to the top jaw of one of the twin
isolating switches, the bottom jaws of these switches being coupled
together. One of these switches controls the connection to the
outgoing feeders, the other controlling the circuit to the spark-gaps,
which are fixed on the outside walls, being connected up to the
switches by small cables passing under the roof. The main circuit
is continued from the isolating switches through series transformers
to the bell-mouths of the three-core feeder cables.
The main alternating-current
instrument board is installed on a gallery in the engine room,
the gear being mounted on 24 polished marble panels. There are
two sets of 100-volt bus-bars carried on the back of this board,
one set carrying the current for the excitation of the main generators,
and the other set supplying the station lighting and the power
for the electrical operation of the high-tension circuit breakers.
The well-known "Tirrill" regulator, supplied by the British
Thomson-Houston Company, is fixed on this board, the instrument
automatically controlling the voltage of the main circuit independently
of speed changes or variation in load.
The generator control desk
is installed on the gallery in front of the main alternating-current
switchboard. There are six generator panels, each with its various
controls and instruments. At the ends of the control desk are two
panels carrying synchronising voltmeters, the synchronism
indicator, and two synchronising lamps.
Interior of Partick Sub-Station
The electrically-operated
engine room telegraphs were supplied by Messrs. Evershed and
Vignoles. They are used for signalling orders to the engine driver
at each of the main generators.
The direct-current
500-volt switchboard is erected on the engine room floor level
underneath the high-tension operating gallery previously mentioned.
This board controls the 500-volt generators, rotary converters,
night load feeders, and the station power supply.
SUB-STATIONS.
There are in all six sub-stations
situated in different districts of the city, containing 26 units,
as under :
Coplawhill 5 ...Dalhousie
6 ...Kinning Park 4 ...Whitevale 5 ...Partick 4 ...Rutherglen 2
Each unit consists of three
transformers of 200 kw. each, and one rotary converter of 500 kw.
Each sub-station has two switchboards, one for alternating current
and the other for direct current. All high-tension switch gear
is erected in separate switch rooms, which contain the necessary
oil switches, etc., operated by remote control from the alternating-current
switchboard.
Each set of transformers,
which are connected in mesh, are placed in a brick chamber, completely
isolated by brickwork and iron floors from the rest of the plant.
The transformers are of the oil-cooled type. Tappings are taken
off the primary winding, so that with 6,500 volts on the
primary, the windings can be plugged so as to give 310, 330, or 350 volts
on the secondary winding. The rotary converters are each of 500 kw. capacity.
They are six-pole machines, running at a speed of 500 revolutions per minute.
The machines are over-compounded to give 500 to 550 volts. The efficiency
at full load is 95 per cent., three-quarter load 94 per cent., half load
92.5 per cent. On the alternating-current end of the rotary shaft a io-h.p.
starting induction motor is fixed for purposes of running the rotary up to
synchronism. On the other end of the shaft a continuous-current booster is
fixed for dealing with part of the return current. The booster is rated at
30 kw. at 50 volts, at a speed of 500 revolutions per minute. The fields
are excited by a portion of the feeder current. Shunt resistances are so
arranged that 200, 400, or 600 amperes can be passed round the field, or
the field can be short circuited. All the electrical equipment was supplied
by the British Westinghouse Company, except the direct-current switchboard
in the Rutherglen sub-station, which came from the British Thomson-Houston
Company.
CABLES.
From the main power-station
run 22 three-core extra high-tension cables, four to each of five
sub-stations and two to the electricity department, the cross-section
area of each core being from .10 sq. in. to .2 sq. in. The cables
are insulated with manila paper impregnated with
an insulating oil and lead
sheathed. In addition, single core 500-volt direct-current feeders
are run to each sub-station, these cables being used for supplying
current to the system during the hours when there is little or
no demand for power for traction purposes.
The three-core cables enter
the sub-stations from ducts into a cable race, and are then split
inside trifurcating heads into three separate rubber-insulated
single cables, and thence led to the feeder oil switches in the
high-tension switch rooms.
From the direct-current
switchboards of the sub-station the 500 volt feeder cables are
led along the cable race into the ducts to the various feeder pillars
in the streets. These feeder cables (some 80 in number) have cross
sectional areas from .8 sq. in. down to .4 sq. in., some of the
feeders to heavy sections being duplicated.

Cable Transporter Car
The distributor cables,
ranging in size from .8 sq. in. to .2sq. in., run from
the feeder pillars to numerous distributing switch pillars. Throughout
the central parts of the city, adjoining feeder areas can be interconnected
by cables running between the nearest switch pillars, a system
of ring mains being thus formed, so that any necessary repairs
in case of the breakdown of any cable can be speedily carried out
without causing undue delay to the traffic.
Negative feeders, numbering
31 in all, used for boosting the return current from the rails,
are laid to the heavily-loaded and more distant parts of the system.
These cables have a cross sectional area of .8 sq. in. or .6 sq.
in. each, and a total area of 21.0 sq. in.
The total length of cables
used in connection with the tramways amounts to about 469.16 miles,
made up as follows :

DUCTS AND MANHOLES.
Most of the ducts are formed
of a riveted lapping of sheet iron of No. 25 S.W.G. (i.e., •02
in. thick) lined with a special cement 9/16 in. thick. The ducts
are laid between the tramway tracks. The bottom tier is laid on
a bed of concrete 3 in. thick, and each tier is covered with
cement, while concrete is laid at the sides and on the top to a
depth of 3 in., the whole forming a nest of cement-lined pipes
embedded in a solid mass of concrete. In some parts of the city
Doulton conduits and ordinary fire-clay pipes, and in others iron
pipes are used.
The manholes are built of
brickwork, the roof being supported by old tramway rails. The manholes
are placed at extreme distances of over 400 ft. apart on straight
runs, to a minimum of about 50 ft. on sharp curves.
Under the Forth and Clyde
Canal the cables are carried in a tunnel surrounded by concrete,
and lined with cast iron tubes.
On some of the extensions
Sykes and fibre ducts have been used, and on others the cables
have been laid solid in Howard asphalt troughing.
TELEPHONES.
A very complete system of
telephones has been laid down, and may be divided into the following
circuits : (1) Head office to main power-station, sub-stations,
car sheds or depots, car
works, and residences of
the principal officials and their assistants ; (2) head office
to numerous telephone pillars erected on the streets, keys of which
are carried by every car and each inspector and timekeeper ; (3)
power-station to each substation ; (4) "emergency system" from
each sub-station to every feeder and distributing switch pillar
within its own area of supply.
OVERHEAD EQUIPMENT.
The overhead equipment for
the original tramway system was carried out by the British Westinghouse
Company. On subsequent extensions the work has been executed
by the staff of the tramway department. Centre poles are used on
several short lengths of route, but on all the rest of the system
span-wire construction has been adopted. Wherever possible the
span wire is attached to the buildings by means of rosettes on
either side of the street.

Moter
Tower Wagans
The trolley span wire is
of 7 strand No. 12 S.W.G. with a breaking strain of 4,000 lb.,
and the guard span wire of 7 strand No. 14 S.W.G. wire with a breaking
strain of 2,000 lb. The guard wire is earthed at each end of every
eight spans. The poles are earthed to the rails with rail bonds
made up to the required length with ordinary trolley wire. The
system is divided into half-mile sections.
Most complete arrangements
are in force for the maintenance and repair of the overhead equipment.
In recent years the horse tower wagons have been displaced by those
of the motor variety, with very satisfactory results. A view of
these motor wagons is given above.

Standard Top-Covered Vestibuled
Car

Testing Car
The total number of cars
owned by the Corporation is now 803, as under :
Top-covered Cars .. .. ..
.. ....................... 621
Double-deck Cars (without
top-covers) .. .. 71
Converted Horse Cars ..
.. ........................ 110
School Car .. .. .. .. ..
................................... 1
Total .. ....................................................
803
The whole of the cars, with
the exception of about 80, have been built and equipped in the
Corporation car works.
The double-deck car with
top roof is carried on a single truck with 6 ft. wheel base, weighs
about 9 tons 15 cwt., and stands 16 ft. 1 in. high over all. The
body is 17 ft. over all, with 6 ft. platforms, the inside having
a seating capacity for 24 passengers. The upper body of the car
is 17 ft. over all, and is fitted with garden
seats, accommodating 28 passengers inside under cover, and 10 passengers
on outside seats. All cars have the trigger gate type of life-guard. Fifty
additional cars are in course of construction. The Standard Car. The
covered car with vestibules has now been adopted as the standard car of the
system. In its evolution from the old type of open-top car a great many alterations
had to be made. The car body is all that remains of the old type. When it
was decided to have top covers it was found that the platform had to be lengthened
to allow of an easily ascended stair being led up to the canopy. This necessitated
the platform bearers being lengthened and new dashes made, wiring to controllers
spliced, and all platform gear made correspondingly longer. The canopy and
upper part are new. When covered cars had been in service for some time the
question of vestibules was considered. Vestibules were fitted to several
top-covered cars, and were so satisfactory that it was decided to fit vestibules
on all cars. These additions and alterations to the car raised another question
that of stability. It was found that the increased length of platform and
the added height had altered the centre of gravity, and, therefore, the car
pitched more than was notice able on the smaller type of car. The remedy
for this was found to be a truck with longer wheel base, and as this truck
must combine stability without undue wear on the wheel flanges or rails at
curves, experiments were made, and it was found that the present truck lengthened
to 7 ft. wheel centres gave satisfactory results. This alteration meant that
the underframing had to be altered to accommodate the wheels. The platform
bearers had to be shortened to clear the wheels, and the magnetic brake and
hand-brake gear altered to suit the increased length of wheel base.
All improvements are now
in hand, and cars, in the course of a few weeks, will be turned
out at the rate of five per week, fitted with lengthened truck,
top roof, and vestibules.
CAR SHEDS.
There are in all nine car
sheds, situated as under:
West End......................
Partick.
North ...........................
Possilpark and Maryhill.
East End ........................Dennistonn,
Whitevale, and Dalmarnock.
South .. ..........................Newlands,
Langside, and Kinning Park.
There is accommodation at these
depots for 1,117 cars. Newlands and Langside can each take 180
cars. Most of the depots were originally built for horse cars,
and were afterwards altered. The number of tracks in all the depots
is 161, and the total length of these tracks is over eight miles.
At all the sheds there are office accommodation, lavatories, washing
room, baths, kitchen, recreation room, gymnasium, etc. The latest
depot, built at Newlands, is much on the same lines for car storage
as the others. In view of the fact that a great percentage of cars
are now covered, gangways have been suspended from the roof along
the entire length of each line, thus enabling the outside of cars
to be cleaned without the use of steps. The principal feature at
this depot is the heating arrangement. Hot water, especially in
winter, is an absolute necessity if cars are to be kept clean.
Newlands
Plan
A vertical boiler has been
installed, which by steam heat through one calorifier supplies
hot water to taps conveniently placed throughout the depot, the
temperature of the water being 120 deg. Fahr., or higher, if desired.
As there is a return pipe to the calorifier, a continuous circulation
of water is kept up, so that hot water can be drawn from any tap
without loss of time. The capacity of this calorifier is 750 gallons
of water per hour. Another calorifier supplies hot water to radiators,
which heat up the depot buildings including hall (seating 300 persons),
kitchen, recreation room, cleaners' store, depot store, and workshop,
and in addition to these buildings there are a fully equipped lavatory
and bathrooms supplied with hot water from the domestic supply.
This hot water installation requires very little attention, the
boiler feed and temperature of calorifiers being automatically
regulated.
CAR WORKS AND CAR BUILDING.
A ground plan of the large
and complete car building and repairing works at Coplawhill, together
with internal views, are here given.
The following is a list
of the staff employed at the car works:
The various departments
are all well equipped with machine tools, etc. The whole of the
cars undergo an annual examination and overhaul in addition to
repairs which they at any time require. The number dealt with at
a time is proportioned so that the whole may be got over in the
year.
In the construction of car
bodies great care is exercised in selecting timber of the very
best quality. For the general framework the best dry Moulmein teak
is largely used. The underframing is of massive design. The
roof ribs are of best English ash, every alternate rib having mild
steel carlines 1 1/4 in. by 1/4 in. on each side. The roof is double
lined, and between the linings canvas, thoroughly stretched and
saturated with genuine white lead, is placed. The panels are of
Honduras mahogany. The inside finishing is in teak panelling
with mahogany mouldings, the ceiling being of three-ply bird's-eye
maple, picked out in gold lines and ornamental corners.
Coplawhill
Works Plan

Car Body Shop Coplawhill Car Works
Carpenters Shop Coplawhill Car Works

Machine Shop Coplawhill Car Works

Overhauling and Repair Shop Coplawhill Works
NOTES
ON TRAFFIC WORK.
Arrangement of Duties. Motormen
and conductors are divided into three classes :
1 Men operating workmen's
or early morning cars. These men are promoted by seniority. They
always report early, and always finish early, being confined to
the early morning cars alone.
2.—Men on regular
duties. These men operate, in their turn, each of the regular duties
allocated to the depot at which they are employed, excluding, of
course, the early morning cars.
3.—Spare men. These
men are employed on the spare list, and advance according to seniority
to any vacancies on the regular duties.
For early morning and regular
men the duties are changed weekly. Spare men are paid full wages
according to scale from the day on which they begin to learn their
duties. If there is no work for them on a car they are employed
about the depot or on the road at some useful work, and receive
a full day's wage for each day they are on duty.
Ticket Check. The
ticket check system in operation is of the usual bell-punch type,
and a staff of inspectors are employed for boarding the cars for
checking purposes.
Two-Stage Fare. On
January 15, 1911, a special " two-stage" fare was introduced.
A passenger, on paying 1 1/2d., receives from the conductor a yellow
ticket which entitles him to travel two consecutive 1/2d. stages
on the car on which it is issued, an average distance of 1.16 miles.
The ticket is retained, and on production at any future time on
any car on any route, is valid for two stages on the second car.
The result of the introduction of this fare was reported on by
the general manager recently. The average number of two-stage tickets
issued is approximately 315,000 per week. As this figure has remained
stationary for some time, it may be taken as a maximum.
Fares. There are
no special fares for workmen, all passengers on the Glasgow system
paying alike.
Cash Collection. Some
years ago arrangements were made that conductors should pay in
cash only on the finish of the relief, instead of each journey
as formerly, and the tendency recently has been to do away, as
far as possible, with cash offices except on specially busy routes
where they are still necessary as a relief to the work of the depot
clerks. The result of this change has enabled the department to
cut down the lying time at termini to a minimum, and has caused
considerable saving in the expenses of cash collection and check.
Bonus to Motormen. A
bonus of 26s. is paid to each motorman on the steady driving list
whose record is otherwise satisfactory, and who has been free from
collision or accidents for a period of half a year that is, 26
clear weeks. This, of course, applies only to accidents which have
been caused or contributed to by the motorman through neglect or
carelessness. The system of working the bonus is exceedingly simple.
When a man is transferred to the driving list a premium or bonus
card is issued to him. This card is signed by the traffic superintendent,
and when a man is called to the head office in connection with
any accident he has to bring the card with him. If the superintendent
is of opinion that the motorman is to blame an entry is made on
the card, and whenever a motorman finds, from his card, that he
has 26 weeks clear without an entry he forwards the card to the
head office, and the bonus is paid with the next week's wages,
the card being returned to the motorman, who signs for the receipt
of the bonus. There is thus very little trouble in working the
system, as the men can be relied upon to claim the bonus whenever
it falls due. The result of the introduction of this scheme has
been very satisfactory, and considerably over go per cent, of the
men regularly earn this bonus, which is equivalent to an extra
1s. per week on their wages.
Training of Traffic
Staff All men employed in the traffic department enter the
service as conductors. The period of training for a conductor
extends to eight days, this time being spent on a car under,
the tuition of an experienced conductor. During the period of
training the learner is frequently visited by ticket inspectors,
and at the finish of the course he is put through an oral examination
to test his qualifications. If satisfactory, the practice note
is signed by the teacher, the ticket inspector, and the depot
clerk, and the man is placed on the spare list. All conductors,
after serving a period varying from 12 to 18. months, are sent
to the motor school. The school is under the control of the traffic
superintendent, and the instruction is given by a qualified electrical
engineer. Four or five days are spent in the school, and the
embryo motorman is then put on the road under the charge of a
skilled motorman. Two motor inspectors, under the chief motor
instructor, pay special attention to the learners, and after
a period on the road they are sent back to the school to undergo
a preliminary examination.

Glasgow Corporation Tramways School for Motormen
At this preliminary examination, it is easily
ascertained whether the learner is likely to turn out a satisfactory
motorman or not. If there is any dubiety, the man is not retained
in the service. If the progress has been satisfactory, however,
he goes back on the road again, and at the end of 14 days undergoes
a final examination at the motor school. If satisfactory, he is
sent to drive a car for 30 days by himself, and if at the end of
this time the officials are still satisfied as to his ability,
he is passed as a qualified motorman. Periodical examinations are
conducted at the depots to see that the men retain the knowledge
which they have gained in their early instruction, and any men
who fail to answer the requirements are either discharged or sent
back to the school for further instruction at their own expense.
Conductors who have qualified as motormen are required to
put in, at least, 14 consecutive days each year as motormen, to
give the men an opportunity of keeping familiar with the duties.
All employees now receive six days holiday per annum with pay.
MEN'S AMBULANCE TRAINING.
Special encouragement has
been given to the men to take training in ambulance work. This
year a team representing the department won the Cowan Cup, which
is the most important ambulance trophy in Scotland. This is the
fifth time this trophy has been won by the Corporation tramway
employees.
UNIFORMS.
All the traffic staff, including
motormen, conductors, ticket inspectors, timekeepers, trolley
and point boys, are supplied with uniform as under :

The men engaged at the overhead
repairs are supplied with leather rainproof coats, gloves, and
rubber boots, and these are repaired when required. All the permanent
way inspectors are supplied with a waterproof coat each year.
FRIENDLY
SOCIETY.
In connection with the department
there is a Friendly Society, each member contributing 6d. weekly,
to which the Corporation adds 4d., making iod. weekly set aside
for each member. The Friendly Society has a membership of 4,000.
Membership is voluntary and confined to employees of the department,
but it is open to all grades of the service. The benefits given
are: In cases of sickness 15s. per week for the first six months,
and 10s. for second six months, and 5s. per week for following
year; at death of a member £20 ; at death of a member's wife £5
; medical attendance and cars on each route, the car-mileage on
each route, the total receipts, and the receipts per car-mile.
Another statement giving similar information for the week is submitted
to him with a note of the number of passengers carried at each
fare. In addition to the calculation per car-mile, the receipts
on each route are brought out per car-hour. Numerous statements
are submitted to the general manager weekly, giving full details
of all expenditure. The wages paid amount to over £7,000
weekly. The total amount paid is allocated to the various accounts
chargeable, and worked out per car-mile and per car-hour. The amount
expended in the maintenance of permanent way, power plant, cars,
etc., is also worked out per car-mile, so that from week to week
all items of expenditure can be carefully watched and regulated.
Copies of all these statements are prepared for the heads of the
various departments for their information and guidance.
FINANCIAL.
The following is an abstract
of the revenue and expenditure for the year to May 31, 1911, as
compared with the figures for the preceding year:

The number of car-miles
run during the year was 21,704,237, and the number of passengers
carried reached a total of 237,967,307.
The total capital expenditure
from 1871 to 1911 amounted to £3,921,406 .10s. 1d. This sum
has been written down to £1,800,259 3s. 1d.
In the accounts for the
past year revenue has been charged with £85,450, to meet
the wear and tear of the track. This sum is calculated at the rate
of £440 per mile of single track, and is in addition to the
usual expenses for ordinary maintenance. The sum laid aside will
be sufficient to completely renew the track every ten years.
In addition to the above,
the revenue of the year is charged with sums to meet depreciation
at the following percentages on the original cost:
The total amount set aside
to meet depreciation and permanent way renewals for the year
to May 31, 1911, was £202,579. These sums are charged in
addition to the cost of ordinary repairs, and also in addition
to the statutory sinking fund of £89,794. After meeting all
working expenses and fixed charges the department had still
a net profit of £68,678, which in terms of section 30 of
the Glasgow Corporation Act, 1909, falls to be paid over to the
Common Good Fund of the city. The following comparative records
show the great expansion of the Glasgow system. In connection with
them it will be noted that the payments to the Common Good have
gone up enormously. The reason is that until the passing of the
Act of 1909 the Corporation only paid to the Common Good a part
of the tramway profits, the rest going into the special depreciation
fund. Since the Act mentioned, however, all profit left after making
allowance for ordinary depreciation goes into the Common Good.

© The
Tramway and Railway World
|